Project Description
GARDEN ISLES WATER MAIN REPLACEMENT project includes:
- Replacement of existing infrastructure with new ductile iron pipe (DIP) water main and associated fittings, valves, service lines, fire hydrants, and appurtenances by CES Construction.
- Installation of sewer point of service cleanouts to those properties lacking them.
- Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
- Pressure testing, bacteriological testing, and density testing.
TIMELINE
Phase 1 improvements have been completed and included Hickory Drive, East of Larch Avenue, Oak Street and Locust Street. Phase 2 consist of Hickory Drive west of Larch Avenue, Larch Avenue and Larch Court. Phase 2 improvements are currently underway and are anticipated to be completed early 2023. Phase 3 includes Magnolia Street and Magnolia Court and is anticipated to be completed by mid-2023.